Bridge Demolition Completed 23 Hours Ahead of Schedule on M67
This weekend our Sheffield Team completed the 2nd phase of a Bridge Demolition job for long standing client S. Evans & Sons Ltd on the National Highways St Annes Road Bridge replacement project on the M67 near Stockport.
This phase of the works involved the Diamond Wiresaw Cutting of both bridge abutments into sections for removal by crane and were scheduled to be complete by 05.30 on Sunday morning but with 2 Hilti WS30 Wiresaws working the job was completed safely and 23 hours ahead of programme.
Its all about having the right people with the right equipment working together.